The Department is headed by a Director and has Four Divisions.
NO. |
SERVICE |
TIME FRAME |
PROCESSES/PROCEDUR ES |
REQUIREMENT(S) FROM CLIENTS |
1 |
Environmental Implication Study (EIS) |
Within Two (2) weeks after the approval of ToR |
EIS Registration/TOR Submission
|
Payment of the sum of four hundred and fifty thousand Naira (N450,000.00) only |
Site verification |
Clearing of site before this exercise customarily attracts penalty of One Million Naira (N1,000,000.00) only, against the proponent. |
|||
Within One Month after Site Verification |
Field Sampling/Data Gathering |
|||
Within Two months after Site Verification exercise |
Submission of Draft Report |
Payment of the sum of three hundred and fifty thousand naira Only (N350,000.00) |
||
Within One month after Draft report submission |
Committee Review/Site Visit |
|||
Within Two weeks for Final EIS report approval |
Final EIS Report’s Approval for commencement of IMM OR Rejection of reports for Re- Submission of Final Reports |
|||
Three months each for IMM Exercises |
Impact Mitigation Monitoring(IMM) 1 st IMM (Construction Phase) 2 nd IMM (Operational Phase) |
|||
After Closure of IMM |
Issuance of Certificate |
|||
After Collection of Certificate (Annually) |
Environmental Compliance Monitoring (ECM) |
|||
After Five (5) years |
Renewal of Certificate |
Payment of the sum of Two Hundred and Fifty Thousand Naira (N250,000.00) only |
||
2 |
Mortuary EIS Approval |
|
Collection of application form |
Ten Thousand Naira (N10,000.00) Only |
|
Submission of ToR and Evidence of Payment |
Two Hundred and Fifty Thousand Naira (N250,000.00) Only |
||
Within Two (2) weeks after submission of form |
Site Verification |
|||
Within Two (2) months after site verification |
Submission of Draft Report |
Payment of Administrative Charge of N 50,000.00 |
||
Within Two weeks of (e) |
In-house Review of Draft Report by the Ministry |
|||
Within Two (2) weeks of (f) |
Forwarding of Harmonised Comment to the Proponent |
|||
Within Two (2) weeks of (g) |
Submission of final Report to the Ministry |
|||
Within Two (2) weeks of (h) |
Final EIS Report’s Approval for commencement of IMM OR Rejection of reports for Re- Submission of Final Reports |
|||
Within Three (3) months of (i) |
Impact Mitigation Monitoring(IMM) |
|||
After Closure of (i) |
Issuance of EIS Certificate |
|||
3. |
Mining and Dredging |
|
Collection of application form |
Twenty Thousand Naira (N20,000.00) Only |
Within Two (2) Weeks of (a) |
Site Verification Exercise Submission of Application Form and a Bank Draft |
Two Hundred Thousand Naira to Six Hundred Thousand Naira (N200,000.00 – N600,000.00) Only depending on the Category |
||
|
Within One (1) Month of (b) and (c) |
Stakeholder’s Forum |
||
Within Two (2) Months of (d) |
Submission of EIS and RP Draft Report |
|||
Within One month after Draft report submission |
Committee Review/Site Visit |
|||
Within One (1) Month of (f)
|
Submission of Final EIS and RP Report |
|||
Within Two (2) Weeks of (g) |
Issuance of EIS and RP permit |
|||
Yearly Submission of Restoration Status Report |
Between One Hundred Thousand and Two Hundred Thousand Naira Only (N100,000.00 – N200,000.00) |
|||
4. |
Accreditation of Consultants |
a) Application Letter b) Certificate of incorporation c) Evidence of payment of registration/Renewal d) Three (3) years evidence of tax clearance; e) Brief introduction of the company f) Company management structure g) Profile of management team h) Profile of operation staff and personnel i) Core activities or areas of operations j) Evidence of partnership agreement or retainership with experts (individual or organisation) in field outside the core competence of the firm`s management or personnel k) Evidence of ownership of functional laboratory, instruments and equipment (in-situ and or laboratory desktops)-provide evidence of on retainership agreement with third party laboratory l) Briefs on most jobs executed m) Evidence of training and capacity building re-education attended and or organised n) Evidence of membership of professional bodies (either at individual and or corporate levels) o) Existing environmental consultancy retainership agreement with industrial or similar facilities in Ogun state; or elsewhere |
Payment of N 100,000.00 for Registration/Renewal |
Other services of the Department include:
Division of Policy Matters