1

Environmental Implication Study (EIS)

Within Two (2) weeks after the approval of ToR

EIS Registration/TOR Submission

Payment of the sum of four hundred and fifty thousand Naira (N450,000.00) only

Site verification

Clearing of site before this exercise customarily attracts penalty of One Million Naira (N1,000,000.00) only, against the proponent.

Within One Month after Site Verification

Field Sampling/Data Gathering

Within Two months after Site Verification exercise

Submission of Draft Report

Payment of the sum of three hundred and fifty thousand naira Only (N350,000.00)

Within One month after Draft report submission

Committee Review/Site Visit

Within Two weeks for Final EIS report approval

Final EIS Report’s Approval for commencement of IMM OR Rejection of reports for Re- Submission of Final Reports

Three months each for IMM Exercises

Impact Mitigation Monitoring(IMM)

1 st IMM (Construction Phase)

2 nd IMM (Operational Phase)

After Closure of IMM

Issuance of Certificate

After Collection of Certificate (Annually)

Environmental Compliance Monitoring (ECM)

After Five (5) years

Renewal of Certificate

Payment of the sum of Two Hundred and Fifty Thousand Naira (N250,000.00) only

2

Mortuary EIS Approval

Collection of application form

Ten Thousand Naira (N10,000.00) Only

Submission of ToR and Evidence of Payment

Two Hundred and Fifty Thousand Naira (N250,000.00) Only

Within Two (2) weeks after submission of form

Site Verification

Within Two (2) months after site verification

Submission of Draft Report

Payment of Administrative Charge of N 50,000.00

Within Two weeks of (e)

In-house Review of Draft Report by the Ministry

Within Two (2) weeks of (f)

Forwarding of Harmonised Comment to the Proponent

Within Two (2) weeks of (g)

Submission of final Report to the Ministry

Within Two (2) weeks of (h)

Final EIS Report’s Approval for commencement of IMM OR Rejection of reports for Re- Submission of Final Reports

Within Three (3) months of (i)

Impact Mitigation Monitoring(IMM)

After Closure of (i)

Issuance of EIS Certificate

3.

Mining and Dredging

Collection of application form

Twenty Thousand Naira (N20,000.00) Only

Within Two (2) Weeks of (a)

Site Verification Exercise

Submission of Application Form and a Bank Draft

Two Hundred Thousand Naira to Six Hundred Thousand Naira (N200,000.00 – N600,000.00) Only depending on the Category

Within One (1) Month of (b) and (c)

Stakeholder’s Forum

Within Two (2) Months of (d)

Submission of EIS and RP Draft Report

Within One month after Draft report submission

Committee Review/Site Visit

Within One (1) Month of (f)

Submission of Final EIS and RP Report

Within Two (2) Weeks of (g)

Issuance of EIS and RP permit

Yearly Submission of Restoration Status Report

Between One Hundred Thousand and Two Hundred Thousand Naira Only (N100,000.00 – N200,000.00)

4.

Accreditation of Consultants

a) Application Letter

b) Certificate of incorporation

c) Evidence of payment of registration/Renewal

d) Three (3) years evidence of tax clearance;

e) Brief introduction of the company

f) Company management structure

g) Profile of management team

h) Profile of operation staff and personnel

i) Core activities or areas of operations

j) Evidence of partnership agreement or retainership with experts (individual or organisation) in field outside the core competence of the firm`s management or personnel

k) Evidence of ownership of functional laboratory, instruments and equipment (in-situ and or laboratory desktops)-provide evidence of on retainership agreement with third party laboratory

l) Briefs on most jobs executed

m) Evidence of training and capacity building re-education attended and or organised

n) Evidence of membership of professional bodies (either at individual and or corporate levels)

o) Existing environmental consultancy retainership agreement with industrial or similar facilities in Ogun state; or elsewhere

Payment of N 100,000.00 for Registration/Renewal


Other services of the Department include:
Division of Policy Matters

  • Registration of new projects, Environmental Implication Study (EIS) Revenue recoding, coordination of training, workshops, conferences, seminars, EIS Budget and the Site Verification of new projects;
  • Coordination of the implementation of green economy for sustainable development in the State;
  • Coordination of all multilateral and bilateral matters such as conference on sustainable development (CSD), African Ministerial conference on Environment (AMCEN), UNGA, etc;
  • Collection, Collation, Analysis, Interpretation and Publication of Information for Policy Making;
  • Publication on Environmental Matters;
  • Development of Policy;
  • Legislative Drafting; and
  • Technical Design.
Division of Planning and Development
  • National Environmental Action Plan;
  • Remote Sensing and GIS;
  • Coordination of Multilateral Environmental Programmes (World Bank, UNDP, UNIDO, GEF);
  • National Council on Environment (NCE); and
  • World Environment Day Celebration.
Division of Research and Statistics
  • Data Banking;
  • Data Analysis and Processing;
  • Library Service;
  • Establishment and Maintenance of the Agencies’ Electronic Database;
  • Computerize the activities of the Agency for an efficient Management Information System;
  • Collecting User requirements and initiating ideas for Software Development; Recommendation of Information System Gadgets and Services; and Sales of Statistical Publication.
Media Division
  • Relationship Management with print and Electronic Media:
  • Media Exposure in Print and Electronic Media;
  • Coverage of Events and Activities;
  • Environmental Impact Assessment (EIA) Public Display; and
  • Maintaining Photo and Video Archives.

Mr. Akinwande K. S

Director of Planning, Research and Statistics